- No ESG compliance = no loan disbursement.
- No documented supervision = no approval of construction progress.
- No Owner’s Engineer (OE) verification = no release of milestone payments.
- No regulatory and ESG proof at commissioning = no commercial operation date (COD).
- lose its operating permit
- trigger fines and shutdowns
- suffer reputational risk that affects the borrower’s ability to repay
- become uninsurable
- become a stranded asset before producing revenue
- The physical work has been completed.
- The work was completed in compliance with permits, labour laws, HSE rules, environmental conditions, and equipment certification rules.
| Traditional role | Modern expanded role |
| Technical supervisor of construction | Verifier of ESG, regulatory and permit compliance |
| Quality assurance authority | Certifier of eligibility for financing drawdowns |
| Interface between Owner and EPC | Independent risk-signal sender to the bank |
- independent from the EPC contractor
- technically competent to assess equipment, supervision, construction, and commissioning
- able to verify compliance against Serbian law, permits, and lender ESG conditions
- contractually authorised to stop or delay payment disbursement if risks are found
- ESG covenants (mandatory obligations written into the loan contract)
- Disbursement Conditions Precedent (documents required before any first payment is released)
- Milestone Verification Conditions (each loan tranche tied to OE-approved progress)
- Suspension Triggers (events that freeze payments — e.g. construction violation, labour incident, missing permit)
- Cure Periods (time allowed for Owner to correct ESG or regulatory breach)
- EPC submits progress certificate
- Owner reviews and signs
- OE conducts field verification + compliance check
- OE issues independent confirmation to bank
- Bank authorises disbursement
- delays payment pending corrective action
- pays into escrow (not directly to EPC)
- freezes all future tranches until breach is resolved
- under-report environmental risk,
- bypass local labour rules,
- outsource work to unqualified subcontractors,
- accelerate works without full permitting,
- install cheaper non-certified equipment,
- treat documentation as a post-completion formality.
- Improper waste disposal → Inspectorate order → Bank freezes drawdown → 7-month delay
- Lack of certified safety equipment → OE refuses sign-off → Bank withholds progress payment
- Unlicensed subcontractor labour → breach of loan covenant → forced contractor replacement
- Transformer installed without oil spill containment permit → commissioning blocked → revenue start delayed
- releases final payment
- activates long-term loan amortisation
- requires proof that the facility is legally operable
- may transition from construction risk to revenue-based repayment
- all permits are in force
- all regulatory inspections are passed
- all equipment is certified and traceable
- no unresolved ESG non-conformities exist
- HSE systems and staffing are operational
- O&M manuals, waste plans, emergency plans, and grid compliance files are complete
